Project Description
Client: DBW Construction
MHL were responsible for all engineering design and engineering supervision on this Sanitary Engineering Project. This contract provided Whitechurch Village with a 3000 P.E. Sewage Treatment Plant and 900cub.m. Water Supply. E.P.S Treatment and Pumping systems provided the detail design and installation of the water tanks and modular treatment plant.
The Waste Water Treatment Plant and Water supply was co-financed by Cork County Council, Castlelands Construction and BDW Construciton and provided Whitechurch Village with sufficient water supply and sewage treatment for the next twenty years.
The treated effluent was pumped 6.5km to Cork City’s Main Drainage System at Kilnap Bridge and the project was completed in 2008.